Chicago Affordable Housing Projects Faced Significant Delays
Only two of thirteen affordable housing projects awarded last year have begun construction, potentially impacting area renters.
Updated on Oct. 9, 2026 in Apartments

Live Poll
Should your local government streamline approval processes to expedite the construction of new affordable housing?
As of mid-September 2026, only two of the 13 housing developments awarded Low-Income Housing Tax Credits (LIHTC) by Chicago in March 2024 have broken ground. This delay affects the city's goal of adding affordable inventory for low-income renter households in Illinois.
Why it matters
The delays are driven by complex municipal approval processes and rising construction costs that have pushed total development expenditures to $562 million. These factors stall the availability of much-needed housing in a market with only 31 affordable units per 100 extremely low-income renters.
Of the 13 projects awarded in 2024, Hub 32 in Garfield Park saw costs rise to $796,000 per unit, a figure significantly higher than state-funded projects. Total development costs for the portfolio reached $562 million, with completion now projected for March 2027.
The players
Chicago Department of Housing
The local government agency responsible for managing federal tax credits and housing approvals.
The details
Developers utilize the LIHTC program by selling tax credits to financial institutions to secure equity for their projects. In Chicago, the process is complicated by the requirement for multiple layers of approvals across various City Hall departments, which can slow progress. Compounding these hurdles, construction expenses have surged, with project-specific costs far exceeding state benchmarks.
Timeline
March 2024: Chicago announced the selection of 13 LIHTC project awards.
Mid-September 2026: Status report showed only two projects were under construction.
End of 2026: Five additional projects are expected to close their financing.
March 2027: The city projects all 13 cycle projects will be completed.
The Home Front
The LIHTC program has financed over 3.9 million housing units since its inception in 1986. These delays reflect broader market pressures and administrative hurdles that can significantly impact the timeline for delivering affordable housing at the municipal level.
Renter households should monitor the status of individual developments through the Chicago Department of Housing for potential application windows as projects move toward completion. Families should prepare for continued competition in the local market where affordable units remain scarce.
The takeaway
Large-scale affordable housing developments face persistent cost and approval delays that impact regional unit availability. Interested residents should continue to track local department updates for their specific neighborhood developments as the 2027 completion target approaches.
Further reading
Learn more about the state of local rental inventory by visiting the Chicago Apartments section.
Live Poll
Should your local government streamline approval processes to expedite the construction of new affordable housing?